Transformation Roadmap 2023–2028
Strategic initiatives, milestones and budget burn across the Helvion IT strategy. Click an initiative for details.
Initiatives
12
5 at risk / delayed
Total budget
€170.2M
Spent to date
€89.6M
53% of budget
Milestones achieved
15/35
202320242025202620272028
◆ green = milestone achieved · ◆ grey = upcoming · filled bar = progress · red line = today
Mainframe Exit (LIDO → Guidewire)
At riskCore Modernisation
Sponsor: Claudia Brenner
01 Jan 2024 → 31 Dec 2027
Progress54%
Budget burn€21.5M / €38M
Milestones
- ✓DE retail book migrated30 Jun 2025
- ○DE commercial book migrated31 Dec 2026
- ○UK run-off migrated30 Jun 2027
- ○Mainframe switched off31 Dec 2027
Impacted applications