Transformation Roadmap 2023–2028
Strategic initiatives, milestones and budget burn across the Helvion IT strategy. Click an initiative for details.
Initiatives
12
5 at risk / delayed
Total budget
€170.2M
Spent to date
€89.6M
53% of budget
Milestones achieved
15/35
202320242025202620272028
◆ green = milestone achieved · ◆ grey = upcoming · filled bar = progress · red line = today
S/4HANA Roll-out TR & PL
On trackEfficiency
Sponsor: Markus Vogel
01 Jul 2025 → 31 Mar 2027
Progress52%
Budget burn€4.5M / €9.8M
Milestones
- ✓PL go-live01 Jul 2026
- ○TR go-live01 Jan 2027
- ○ECC decommission31 Mar 2027